Nevada regulators press Bally’s over Las Vegas stadium project
Chairman Soo Kim told regulators the company could meet its stadium-related obligations by the 2028 baseball season.

Nevada gaming regulators pressed Bally’s Corp Chairman Soo Kim on Thursday about the company’s commitments to a Las Vegas Strip development next to the planned Las Vegas A’s stadium. Kim said Bally’s could meet its obligations in time for the 2028 baseball season.
Nevada Gaming Control Board Chair Mike Dreitzer said he had “significant concerns” about the project’s place among Bally’s priorities, according to iGaming Business. He raised the issue during expedited hearings on Bally’s acquisition of UK operator Evoke through Intralot.
The Nevada Gaming Control Board and Nevada Gaming Commission unanimously granted the sign-offs needed to close the acquisition, iGaming Business reported. Commissioner Richard Schonfeld also raised concerns about whether Bally’s was stretched across its projects, according to CDC Gaming Reports.
Bally’s has pledged a $1.19 billion mixed-use development beside the stadium. The site has seen little progress since the company imploded the former Tropicana in October 2024, iGaming Business reported.
CDC Gaming Reports said Kim assured regulators that Bally’s would cover an initial $250 million in financial obligations for non-gaming businesses connected to the stadium. The company has agreed to build a northeast plaza entrance providing access to Las Vegas Boulevard.
Kim said Bally’s main obligations include a parking structure, utility connections and a connection between the Strip and the ballpark entrance. He told regulators that “each of those obligations can and will be met” by Opening Day of the 2028 MLB season, iGaming Business reported.
The stadium arrangement involves Bally’s, the A’s and Gaming and Leisure Properties, which owns the real estate assets. Kim said the three-party deal added complexity because the other parties must agree on a course of action.
Gaming and Leisure Properties has offered financing subject to matters being settled between Bally’s and the team. The A’s have said “a contingency plan” is needed, iGaming Business reported, citing the Las Vegas Review-Journal.
Bally’s is also developing resorts in Chicago and New York City. The company ended the third quarter with $497 million in cash and $4.8 billion in long-term debt, according to iGaming Business.
Dreitzer told Kim that Bally’s would return before the Control Board and that the regulator was watching the Las Vegas project closely, CDC Gaming Reports reported. Kim said he looked forward to further meetings with the board.