NYC casino developers face new tax dispute, design delay and financing worries
Resorts World disputes $80.6 million in racing payments, Metropolitan Park waits on design approval, and Bally's works through financing worries.

Almost a year after New York State issued three commercial casino licenses for New York City, the successful bidders are running into fresh obstacles as they try to deliver their multibillion-dollar projects, Gambling Insider reported.
Resorts World New York City has already expanded its gaming floor and added table games, but revenue growth has been modest and the company disputes an $80.6 million bill for horse-racing support. Hard Rock Metropolitan Park in Queens is waiting on city design approval, and Bally's has secured initial financing for its Bronx casino at Ferry Point.
Resorts World opened commercial operations with table games on April 28, initially offering 2,500 slot machines and 242 table games. It added another 1,400 slot machines in July and launched a high-limit International Room in October.
New York State Gaming Commission data show Resorts World generated $794.3 million in gross gaming revenue through October. Monthly revenue has held between $122 million and $136 million since May, the first full month of commercial operations.
Between May and October, Resorts World increased its average daily number of slots and electronic table games by 61% to 4,024 units, but revenue from those machines fell 9.5%. Average daily win per unit dropped from $1,275 to $716, while table game revenue doubled since their introduction and rose 54% since mid-May.
Through November 15, the casino had generated $859.6 million since its commercial launch, with 4,137 slots and electronic table games and 345 table games in operation. Resorts World's application projected $2.2 billion in gross gaming revenue by 2027, but its current weekly pace points closer to $1.54 billion, requiring roughly 44% growth to meet the original target.
A separate dispute with the state adds pressure. According to the New York State Gaming Commission, Resorts World owes $80.6 million in statutory horse-racing support payments through October, and the amount could exceed $180 million by June 2027. Because the other two licensees are not expected to open until 2030, Resorts World must cover all such payments and could be on the hook for nearly $500 million until then.
Resorts World argues it should be able to deduct those payments from its total taxes, but the state says the obligation is separate. The company committed to a 56% tax rate on slot revenue and 30% on table game revenue; paying the racing support on top would push its effective slot tax burden to about 72%. An interim agreement from October lets Resorts World pay the New York Racing Association directly while talks continue, but the state has not dropped its claim to the outstanding revenue.
Metropolitan Park design vote delayed again
New York City's Public Design Commission postponed a vote on the $8.1 billion Metropolitan Park project on Monday for the second time in just over a month, after a five-hour meeting ran out of time for public testimony. The commission had unanimously tabled the proposal on October 20 and asked for more detail on stormwater mitigation and changes to building façades, pedestrian circulation, and public access.
The developers have since revised the plans, including stormwater management measures. The commission's review covers only building design, but the delay can push back construction. The project was already about five and a half months behind the schedule submitted to state regulators as of May, the Queens Daily Eagle reported. Metropolitan Park gets another chance at a commission vote on November 30.
Bally's financing progresses amid liquidity warning
Bally's announced on October 2 that it secured $400 million in financing led by WhiteHawk Capital Partners for pre-construction costs and other expenses tied to Bally's Bronx. In third-quarter filings, the company said another $160 million remains available for future draws, though the loans carry a high interest rate and mature in April 2028, more than two years before the planned opening of the $4 billion development.
Bally's financial position was a concern for the Gaming Facility Location Board during licensing. In its recent Q3 earnings, Bally's again warned of potential difficulties meeting its debt obligations and disclosed it failed to meet a minimum liquidity requirement at the end of September. The company later announced $560 million in additional financing commitments. Bally's bought the development site for $157 million in February and filed construction permit applications in July; the Public Design Commission granted preliminary approvals for the reconstruction of Ferry Point Park in October and this month.
Bally's plans to begin construction in 2027, while Metropolitan Park's schedule has slipped. Both new-build casinos still target 2030 openings. Resorts World's performance so far offers the first indication of the revenue potential of New York City's commercial casino market.